horso by themebuzz

Construction

FROM VISION TO REALITY

MONTHLY UPDATE

Play Video

OUR COMPLETE JOURNEY TO DATE

Play Video

From Vision to Reality

Alhamdulillah, we are pleased to announce that construction for the Brisbane Islamic Centre is well underway with completion targeted for 2024 at an estimated cost of $18-20 million.

 

You can experience the Mosque and all its wonderful community assets by visiting BIC House Display Centre at 161 Underwood Road, Eight Mile Plains

 

To book you visit call (+61) 468 825 786

Historical Project timeline

This timeline summary briefly outlines the project from inception through to construction commencement.

Project Timeline
Achieved
2007
Brisbane Islamic Centre entity established
2008
Property at 161 Underwood Road, Eight Mile Plains acquired.
2008 – 2012
Preparatory work for Development Approval Application. Lodged in December 2012.
10 July 2015
Application declined by Brisbane City Council
20 July 2015
Appeal lodged in the Planning and Environmental Court
16 December 2016
Development Application Approval granted by the Court 
30 June 2017
Vegetation and Earthworks Approval granted 
December 2017 – August 2018
Vegetation cleared and earthworks completed
August 2018 – March 2019
Architectural and concept design
Consultants preparing plans for Building Approval
June 2020
Minor change Approval granted by Planning and Environmental Court
July 2021
Awaiting Final operational works from the Council for building operational works to commence 
September 2021
Final Building operational works approved
December 2021
Construction commenced
Call Us

0468 825 786

With your support we will be able to enhance your social, spiritual and physical well being, and showcase Islam to Australia Insha’Allah.