Alhamdulillah, we are pleased to announce that construction for the Brisbane Islamic Centre is well underway with completion targeted for 2024 at an estimated cost of $18-20 million.
You can experience the Mosque and all its wonderful community assets by visiting BIC House Display Centre at 161 Underwood Road, Eight Mile Plains
To book you visit call (+61) 468 825 786
Historical Project timeline
This timeline summary briefly outlines the project from inception through to construction commencement.
Project Timeline | Achieved |
2007 | Brisbane Islamic Centre entity established |
2008 | Property at 161 Underwood Road, Eight Mile Plains acquired. |
2008 – 2012 | Preparatory work for Development Approval Application. Lodged in December 2012. |
10 July 2015 | Application declined by Brisbane City Council |
20 July 2015 | Appeal lodged in the Planning and Environmental Court |
16 December 2016 | Development Application Approval granted by the Court |
30 June 2017 | Vegetation and Earthworks Approval granted |
December 2017 – August 2018 | Vegetation cleared and earthworks completed |
August 2018 – March 2019 | Architectural and concept design Consultants preparing plans for Building Approval |
June 2020 | Minor change Approval granted by Planning and Environmental Court |
July 2021 | Awaiting Final operational works from the Council for building operational works to commence |
September 2021 | Final Building operational works approved |
December 2021 | Construction commenced |